Reverse schedule for an ISBI 2005 submission:
- By October 1st (1 month beforehand): complete all experiments
and begin writing up and producing figures from the data
- By September 15th: comparison between the 2 methods (overlap,
Specificity) to produce graphs for validation
- By September 10th: benchmarking and evaluation of registration
(model building)
- By August 20th: results received from overlap-based evaluation
- By August 15th: evaluation based on Specificity and Generalisation
to be completed (processed in parallel with overlap measures for evaluation)
- By August 10th: build 3+ different models using different
registration algorithms, e.g. group-wise, pair-wise and a variant
of the MDL algorithm
- By August 1st: registration quality confirmed to have improved
(based on ground truth)
- By July 20th: high-quality registration of images and labels
to reach a good starting point