Deadlines

See Table [*] for deadlines. The one shown further below (Table [*]) is for personal guidance only.


Table: Stricter deadlines.
  Deadline date
Existing code mastered December 20th, 2003
Submission of Literature Report December 22nd, 2003
Extension to code completed January 5th, 2004
Presentation January - February 2004
Resolving Project Plan (End of) January 2004
Progress Report Submission March 24th, 2004
First implementation working (Late) April 2004
Implementation entirely documented July 2004
Experiments performed August 2004
Continuation Report Viva completed September 1st, 2004